Rover Web v2.0.0 Release Notes ​

Version 2.0.0

These are the release notes for version 2.0.0 (12/9/2024) of the Rover Web application and can be made available to customers running Rover ERP, IMACS and other non-Zumasys owned systems. Contact your Client Success Manager, Sales or Support today!

New Features ​

  • Rover Web
    • Rover AI Assistant
      • The Rover AI Assistant is now available for Enterprise subscribers who utilize Rover BI. AI Assistant is an end-to-end ERP assistant, able to answer questions about the business and also take instruction to perform a myriad of business actions. For more information on Rover AI Assistant, contact your Client Success Manager, SalesRover AI Assistant
    • Point of Sale
      • Custom Part Inventory Lookup tables now support sorting and filtering. POS INV Lookup Filters
      • Custom subtotaling has been added to the POS cart summary view, allowing for integration specific subtotal items such as freight, handling charges, etc to be displayed to the user.

        Note: Currently only supported by select ERPs.

      • Ability to auto-save orders as draft has been added to the user settings.
      • POS Auto Save Toggle

        Note: This option is only available if draft orders are enabled in MRK.CONTROL

      • Input fields in the Order additional information section enhancements:
        • Ability to show field as a toggle has been added. Enable by setting FDICT boolean flag.
        • Ability to validate fields when input has changed has been added. Enable by setting FDICT web_validate flag.
      • Order validation codes have been updated. To view changes navigate to POS Integrations.
    • Customer Inquiry
      • The Opportunities table has been updated to fetch results in smaller batches to improve performance and reliability. Opportunities Lazy Load
      • Improvements to new opportunity creation from within Customer Inquiry. New opportunities are created without leaving the currently selected customer. Newly created opportunities are immediately reflected in the opportunities table.
    • Production Scheduling
      • There is now an option in WO.CONTROL to choose the layout of the scheduling tab in Production Scheduling. The Gantt chart can now be displayed at the top or bottom of the screen.
      • Also in WO.CONTROL there are now settings to allow for custom colors to be applied to Gantt chart items based on the status of the parent Work Order. Gantt Chart Colors -
    • Inventory
      • Inventory Module now supports Form Option Selection upon record save. Custom Info Dialog -
      • Inventory Module now supports display of custom informational dialogs upon record save. These custom dialogs are to support integration specific requirements upon request. Custom Info Dialog -

Bug Fixes ​

  • Rover Web
    • General
      • Errors during customer search operations are now displayed to the user.
    • Point of Sale
      • When an error occurs during a customer search in POS, the search result list is now cleared.
        • Issues with date sort on invoice data table have been resolved.