# Routing Listing (ROUTING.R1)

Read Time: 1 minute(s)

Form Details
Form Details

Purpose
The ROUTING.R1 procedure is used to print routing listings. The user specifies the routings to be printed.

Frequency of Use
As required.

Prerequisites
None.

Data Fields

Oper The operation number defining each step on the routing.
Work Center The work center at which the operation is performed.
Operation Description The multi-line description of the routing step.
Pre-Operation Hours The number of hours that assemblies are queued at the operation before work is started.
Setup Hours The number of hours required for setup at the operation.
Run Hours The number of hours expended at the operation to complete one assembly.
Post-Operation Hours The number of hours required to move assemblies from the operation.
Crew Size The number of persons or machines used concurrently at the operation on the job.