# Routing Mass Update Procedure (ROUTING.P2)

Read Time: 2 minute(s)

Form Details
Form Details

Purpose
The ROUTING.P2 procedure is used to perform a mass delete or add on all routings for specified work centers.

Frequency of Use
As needed.

Prerequisites
The correct information must be present in the work center file.

Data Fields

WORK.CENTER Enter the specified work centers to be added or deleted.
DESCRIPTION Description of the work center as defined in WC.E .
OPER If you will be adding work centers, to the routing then enter the operation number you wish to use. You can leave this field blank if you want the system to automatically re-assign all operation numbers for you. If you do not want the system to re-assign the operations for you this is a required field. ****** WARNING ******** If the operation number already exists in the routing, the work center will not be loaded in.
POS If adding work centers, enter the position in the routing that this work center should be placed. For example, if you enter "3", this work center will become the third operation. If left blank, the work center will be added to the end of the list. This procedure updates all routings. Therefore, if you are adding more than one work center and enter the same position for all of them, the last one in the list will become stored on the specified position. For example, if you are adding two work centers and have specified
position 2, the first work center listed will become the third operation and the 2nd work center list will become the second operation.
FUNCTION Enter an "A" to add the specified work centers to all routings. If the work center already exists it will not be re-loaded or added a second time to the routing.
Enter a "D" to delete the specified work centers from all routings that contain the specified work centers. All occurences of the work center will be deleted from the routing.
REASSIGN.OPER.NO Enter a "Y" if you wish the program to automatically, re- assign the operation numbers. The existing operation numbers will be over- written and numerically re-assigned as 1, 2,
3, etc. depending on their position in the routing. This program does not attempt to update the routings on existing work orders. Enter a "N" or leave blank to not re-assign the operation numbers. If this field is left blank than an operation must be specified for each routing.