The CRP.R2 procedure is used to produce a detailed capacity requirements planning report showing the dates and hours for each individual requirement.

Frequency of Use
As required.

Prerequisites
None.

Data Fields

Wk Ctr The work center whose capacity is being shown.
Description The description of the work center.
Date The date on which the associated capacity requirements occur.
Capacity The hours of capacity defined for the work center on the associated date.
Required The hours of capacity required by each work order on the associated date.
Avail The hours available on each date after deducting the hours required from capacity.
Type The classification of the item placing the demand on capacity.
Id The record ID of the item that requires the capacity (usually a work order number).