# Master Schedule Purge Process (MS.P1)

Read Time: 1 minute(s)

Form Details
Form Details

Purpose
The MS.P1 procedure is used to remove past due dates and quantities from the master schedule records.

Frequency of Use
If you are using the PLAN.E procedure to release work orders from master, schedule items, then you probably do not need to run this process until the next time you are ready to lay out the production schedule. If you release work order manually and do not manually remove the dates and quantities associated with the release from the master schedule, then you will need to run this procedure on a regular basis to remove the dates and quantities consumed so that demand is not inflated.

Prerequisites
None.

Version 8.10.57