# Independent Demand Netting (MRP.P2)

Read Time: 1 minute(s)

Form Details
Form Details

Purpose
The MRP.P2 nets sales order demand against independent demand by period, reducing independent demand that falls within the same period as the sales order. Independent demand will not be reduced below zero for any period. This procedure is an optional process that should be run before MRP.P1 . If this is to be run, then it is critical that the MRP.P1 parameters be set to: Load MPS Requirements = "Y" and Load Independent Demand = "N". This procedure uses the MPS files to do the netting, therefore, it cannot be run if using the MPS system to drive MRP.

Frequency of Use
This procedure is optional, to be used as required, but if used should be run on the same frequency as MRP.P1 .

Prerequisites
None.

Version 8.10.57