# Work Order Labor Variance Report (WO.R7)

Read Time: 1 minute(s)

Form Details
Form Details

Purpose
The WO.R7 procedure is used to print a report of the variance between the labor hours planned for a work order, and the hours actually posted. The report is run for a specified date range, and may be limited to a single assembly. Only work orders that have already been closed are included in the report.

Frequency of Use
As required.

Prerequisites
None.

Data Fields

Work Order The number of the work order.
Date Closed The date on which the work order was closed.
Part Number The part number of the item built by the work order.
Model Number The model number associated with the part number.
Original Quantity The quantity that the work order was defined to build.
Quantity Completed The quantity on the work order that was actually completed.
Work Center The name of each work center identified on the work order routing.
Planned Hours The hours planned for each work center on the work order routing.
Actual Hours The hours that were actually posted to the associated work center.
Variance The difference between the planned and actual hours.
Percent The difference between the planned and actual hours stated as a percentage.