- Added support for a 10 key keyboard on the parts search input field for ease of use on some mobile screens.

# Production Scheduling
- Multiple changes have been made to the production scheduling chart
- If adding an operation for a work order that is part of a phase, all associated operations for that phase will be added as well
- When adding an operation to the schedule, existing conflicting operations will be pushed out to accommodate
- If an operation has a defined list of alternate work centers, it can only be added to one of those work centers defined. When dragging, other work centers will be grayed-out.
- If an issue code is set for a work order, an icon will be displayed on the bars in the chart indicating the issue.

# Bug Fixes
# Rover Web
# Point of Sale
- Addressed an issue with lazy loading of part search results in point of sale.
- Addressed an issue with duplicate fetch of order list, when enabled, after customer selection.
- Addressed an issue with incorrect success message when creating an order. Message now correctly states the order was created rather than a quote.
- Addressed an issue with scanning parts causing duplicate validation requests.
- Addressed an issue with categories not clearing filters on change.
- Addressed an issue with Parts grid view not loading when clearing filters.